Infinity Construction Co., Inc. - Commerical Projects

Key Bank Venture Operations Center - Parma, OH

Description:

 

Complete interior demolition and re-construction of 53,000 SF of office space for the creation of a bank operations center.

Owner:

 

KeyBank

Architect:

 

The Austin Company

Completion:

 

December 2009

Volume:

 

$3,710,600.00

Self-Performed Work:

 

5%




KeyBank Branches – Brunswick/Sheffield, OH       back to top
  

Description:

 

KeyBank purchased two Donato's Pizza buildings and converted them into new 3,000+ SF KeyBank branches.  Each location had all drywall, interior walls, and concrete floors removed before the renovation.  Each location also added a small addition to the building for offices and ATM drive-thru for deposits and withdrawals.

Owner:

 

KeyBank Corporation

Architect:

 

Hengst Stref Bajko / Vocon

Completion:

 

April 2009

Volume:

 

$1,536,750.00

Self-Performed Work:

 

10%



Alliance Bernstein Office at Key Tower, Cleveland, OH       back to top

  

Description:

 

8,800 SF Tenant Buildout.  Office renovation with high end millwork, office fronts, etc.  Conference rooms featured latest AV upgrades.

Owner:

 

Alliance Bernstein

Architect:

 

Gensler, Inc.

Completion:

 

February 2009

Volume:

 

$1,424,200.00

Self-Performed Work:

 

5%




Hahn Loeser + Parks, Cleveland, OH       back to top
   

Description:

 

52,000 SF Tenant Buildout.  Office renovation of the 27th and 28th Floors of 200 Public Square. Featured curved wood stairwell connecting the two floors and wood floor and paneling in the lobby area of the 28th floor.

Owner:

 

Hahn Loeser + Parks, LLP

Architect:

 

NBBJ

Completion:

 

June 2008

Volume:

 

$4,221,000.00

Self-Performed Work:

 

0%




KeyBank Tower & Historic Building Renovation, Cleveland, OH       back to top

Description:

 

The project consisted of replacing flooring, wallpaper, ceramic tile and millwork on 22 occupied floors.  All work was completed after hours and completed in 4 months.  Also included renovating main conference room.

Owner:

 

KeyBank Corporation

Architect:

 

Oliver Design

Completion:

 

December 2007

Volume:

 

$7,976,260.00

Self-Performed Work:

 

5%




PR Newswire, Cleveland, OH       back to top
  

Description:

 

26,000 SF Tenant Buildout.  Office renovation at the Penton Media Building with critical mechanical and electrical components to allow 24 hour use.  Generator was added in the building dock area for emergency back-up situation.

Owner:

 

PR Newswire

Architect:

 

Vocon

Completion:

 

November 2006

Volume:

 

$1,817,995.00

Self-Performed Work:

 

10%




Cleveland Cav's Office at the "Q", Cleveland, OH       back to top
   

Description:

 

Work entailed demolition of existing 2 floors and reconstructing from bare space a open space plan that is the current headquarters of the Cleveland Cavalier's.  An interconnecting stair case was added for a smoother flow of worker access.  Work was completed in 3 months.

Owner:

 

Cleveland Cavaliers

Architect:

 

Vocon

Completion:

 

September 2006

Volume:

 

$2,975,000.00

Self-Performed Work:

 

10%




McDonald Hopkins, Cleveland, OH       back to top
  

Description:

 

Complete interior build-out of new floor space and renovation to existing office space on floors 19 through 22 in the Fifth Third Center Office building totaling 68,000 SF.

Owner:

 

McDonald Hopkins Co., LLP

Architect:

 

NBBJ

Completion:

 

June 2006

Volume:

 

$3,260,275.00

Self-Performed Work:

 

5%




ICI Paints, Strongsville, OH       back to top
  

Description:

 

Renovation of 80,000 SF of office space in 3 months.  This project encompassed all aspects of renovation, one area was carpet and paint only, other areas were complete gut and rebuild and a third area had exterior walls removed and replaced with aluminum window systems.  Since the owner was a paint and coatings manufacturer the majority of the finishes were products which were still in R&D or colors which were not available to the public so Infinity had to work closely with the owner on applications and finish techniques.

Owner:

 

The Glidden Company

Architect:

 

KA Architecture

Completion:

 

February 2005

Volume:

 

$2,300,500.00

Self-Performed Work:

 

5%




Deloitte Touche, Cleveland, OH       back to top
  

Description:

 

50,000 SF Tenant Buildout.  Office renovation of 3 floors at Key Tower.  High end millwork office areas with open areas for the administration staff.

Owner:

 

Deloitte Touche

Architect:

 

Skidmore, Owens, Merrill

Completion:

 

October 2004

Volume:

 

$5,539,370.00

Self-Performed Work:

 

2%




Hahn Loeser + Parks, Akron, OH       back to top
  

Description:

 

Complete interior build-out of 20,000 SF of commercial office space in the GO-JO Office building.

Owner:

 

Hahn Loeser + Parks, LLP

Architect:

 

The Core Group

Completion:

 

October 2004

Volume:

 

$1,368,250.00

Self-Performed Work:

 

2%




Fifth Third Corporate Headquarters, Cleveland, OH       back to top
  

Description:

 

Renovation of existing bank branch located on the first floor was completed in 4 weeks with the remaining 7 floors having extensive modifications to offices, conference rooms and common areas.  All new finishes were installed.  Project was completed in 3 months.  Approximately 70,000 SF of floor space was completed in the project. 

Owner:

 

Fifth Third Bank

Architect:

 

Oliver Design

Completion:

 

September 2004

Volume:

 

$2,975,000.00

Self-Performed Work:

 

5%




Hahn Loeser + Parks, Columbus, OH       back to top
  

Description:

 

Complete interior demolition and build-out of 19,000 SF of commercial office space in the Capitol Square Office building.

Owner:

 

Hahn Loeser + Parks, LLP

Architect:

 

The Core Group

Completion:

 

June 2004

Volume:

 

$1,082,900.00

Self-Performed Work:

 

0%




Fifth Third Bank, Mayfield Heights, OH       back to top
  

Description:

 

New construction of a 5,000 SF 5/3rd Bank branch.  This facility consisted of open teller space and 6 private offices.  The building had 3 drive up windows and 1 ATM drive up.  There was a walk in vault which consisted of a specially reinforced floor slab and precast walls and ceiling. 

Owner:

 

Fifth Third Bank

Architect:

 

Oliver Design

Completion:

 

May 2004

Volume:

 

$1,210,600.00

Self-Performed Work:

 

5%




Heinen's Corporate Headquarters, Warrensville Heights, OH       back to top
  

Description:

 

Project consisted of building from shell space approximately 24,000 SF of office space handling corporate space into one common area.  Space was made up of offices, accounting, marketing, sales and a multitude of conference rooms.

Owner:

 

Heinen’s Corporation

Architect:

 

Oliver Design

Completion:

 

August 2002

Volume:

 

$1,387,650.00

Self-Performed Work:

 

5%




American Cancer Society Community Center, Cleveland, OH       back to top
  

Description:

 

A 2-story steel frame building with masonry and glass/aluminum exterior wall systems.  The Center includes general offices, training facilities, resource and reference libraries, conference rooms, and a 2-story atrium/gallery area.

Owner:

 

Cleveland Clinic

Architect:

 

Van DIJK, PACE, WESTLAKE

Completion:

 

March 2001

Volume:

 

$3,096,820.00

Self-Performed Work:

 

5%




Alcoa Building 53 Renovation, Cleveland, OH       back to top
  

Description:

 

A 56,500 SF interior and exterior conversion of ALCOA’s 5-story Building 53 from industrial use to its Corporate Headquarters for the Forged Wheel Products Division.  The project was lump sum bid, then Infinity was hired to facilitate start of construction while a $500,000 value engineering and re-design took place.  Work included a new 5-story glass atrium structure, all new exterior windows, new elevators, the complete fit-out of 3 floors of office space, and a 3,300 SF lobby on the 1st floor.  All 3 floors utilized a raised computer system with integral under floor air distribution system.  The project was completed in just 7 months.

Owner:

 

Alcoa

Architect:

 

Design Collective

Completion:

 

June 2000

Volume:

 

$5,490,550.00

Self-Performed Work:

 

5%

© Copyright 2009, Infinity Construction Co. Inc
18440 Cranwood Parkway • Warrensville Hts., OH 44128
Phone: 216-663-3777 • Fax: 216-663-3778

Company Info | Services | Projects | Contact Us | General Contractors | Construction Management